Backorders (Network Optimization)

Backorders enable Cosmic Frog’s network optimization engine (Neo) to fulfill customer demand in a later period than the period in which it was due, at a cost that you specify. Instead of forcing every unit to be delivered exactly on time, Neo can weigh the cost of serving late against the cost of the alternatives: building capacity for every peak, prebuilding and holding inventory, or leaving demand unserved. It helps answer questions such as:

  • Is it cheaper to deliver part of a demand peak late than to size the network to serve all of it on time?
  • After a production outage or supply disruption, how much demand is served late, how late, and at what cost?
  • Should we hold prebuilt inventory close to customers, or accept some late deliveries?
  • What is customer tolerance for delay worth to us? What if customers accepted one more period of lateness?

A backorder is demand that is fulfilled in a modeled period later than its original due period.

Backordering is a permission, not a requirement. Neo can still serve demand on time, and it will choose late service only where this lowers the overall cost of the network or where it is the only way to serve the demand.

Backorders are set up with two new fields on the Customer Demand table and are reported in new fields on existing output tables as well as in a new output table, the Optimization Demand Backorder Summary. Backorders can also be combined with stepped costs to make the cost of late delivery depend non-linearly on how late the demand is served.

Quick Start

If you want to get going with backorders quickly, follow these steps:

  1. Use a multi-period model: backorders need later periods in which late demand can be delivered.
  2. Set the cost of late delivery: on the relevant Customer Demand records, specify a Per Unit Backorder Cost.
  3. Optionally limit the delay: enter a whole number greater than 0 in Maximum Backorder Periods to cap how many periods late demand may be served.
  4. Run Neo: no additional model option needs to be enabled; backorders are automatically allowed on the demand records where they are specified.
  5. Review the results: check Total Backorder Cost on the Optimization Network Summary, and the demand period, delivery period, and periods late in the Optimization Demand Backorder Summary.

Alternatively, you can also get started using Ada, Optilogic’s agentic AI, and ask her questions along the way. For example, start with a prompt like “Create a small Neo model which uses the backorder fields on the customer demand table in a scenario. Make sure that in this scenario part of the demand is served late”.

Why Backorders Matter

Many supply chains do not serve every order exactly when it is due. Customers often accept a delay, whether this is explicit (a contractual lead time or delivery window) or implicit (an order that gets shipped once stock arrives). Models that insist on 100% on-time service can overstate the capacity and inventory a network needs and can even be infeasible when a real network would simply deliver somewhat late.

Without backorders, the usual workaround is to leave demand optional (Demand Status = Consider) so that the model can drop what it cannot serve. This hides the difference between demand that is delivered late and demand that is lost altogether.

Backorders let Neo treat late delivery as an optimization decision with its own cost. Late service is then evaluated together with production, sourcing, inventory, and transportation decisions, rather than as a manual after-the-fact adjustment. The outputs quantify how much demand is served late, how late it is, and what this costs.

✓

Pro tip

Backorders and unserved demand are different economic choices. Per Unit Backorder Cost prices demand that is delivered late; Penalty Cost (also on Customer Demand) prices demand that is never served.

‍

When to Use Backorders

Use backorders when customers can accept a delay and you want Neo to decide whether, how much, and how late demand should be served. The following are common situations where backorders may be appropriate:

Rule of thumb question: Is serving demand late a real option that I want Neo to evaluate, with a cost I can put a number on?

  • Yes: Backorders are likely the right tool.
  • No: If demand must always be served in its due period, leave the backorder fields blank. If demand may simply be lost if it cannot be served when due, use Demand Status = Consider, optionally with a Penalty Cost.

How Backorders Work

Customer Demand: Two New Fields

Backorders are configured on each applicable record of the Customer Demand table. Two new fields are available:

Combining the two fields gives the following behavior:

!

Heads up

Late service at no charge is rarely realistic. If you set only Maximum Backorder Periods, Neo can treat late delivery as free, and may deliver late even when on-time service would cost slightly more. It is recommended to specify a Per Unit Backorder Cost whenever backorders are allowed.

‍

Lateness is Counted in Model Periods

The backorder fields do not introduce a separate time unit. Lateness is counted in model periods, not days. With weekly periods, one period late means one week late; with monthly periods it means one month late. Periods of unequal length still count as one period each. Use a period structure that matches the lateness granularity that is meaningful for your business.

A multi-period model is required, because late deliveries need later periods in which to be served. The last period in which demand can be served late is the earlier of: the original demand period plus Maximum Backorder Periods, and the final period of the model (see Handling the End of the Model Horizon).

Demand Status: Include versus Consider

Demand does not need to be set to Consider to allow backorders. As soon as a Per Unit Backorder Cost or Maximum Backorder Periods > 0 is set, backorders are automatically allowed. How Demand Status interacts with this is as follows:

  • Demand Status = Include: all of the demand must still be served, either on time or within its allowed backorder window. Backorders give Neo more flexibility in when to serve, but not whether to serve. If not all demand can be served within the allowed window, the model will be infeasible.
  • Demand Status = Consider: Neo may leave demand unserved if this is more economical, according to revenues, costs, and any Penalty Cost. Backorders add late delivery as another option; they do not require Neo to use it. Think carefully about the backorder cost here: if the backorder cost plus the other costs to serve exceed the revenue (based on a product’s Unit Price), Neo can choose to not serve the demand at all.

Configuring Backorder Costs

Numeric Backorder Cost

When Per Unit Backorder Cost is a number, the backorder cost is calculated as:

Backorder cost = late quantity (/volume/weight) × Per Unit Backorder Cost × periods late

On-time deliveries incur no backorder charge. If one demand record is split over several delivery periods, the cost is calculated separately for each late portion, and the results are added up. Backorder cost is an additional modeled cost; it does not replace production, inventory, transportation, or other costs.

Example: Numeric Cost

Consider the following details of a simple example model:

  • One manufacturing location MFG_1, 1 customer location CZ_1, 1 product Product_1
  • Six weekly periods, P1-P6
  • Initial inventory of 200 units of Product_1 at MFG_1
  • To encourage serving demand as soon as possible, inventory holding costs are modeled:
    • Unit Value of $50 (Products table)
    • Inventory Carrying Cost Percentage of 20% (Model Settings table)
  • Due to a disruption, MFG_1 cannot produce anything during P1-P4; no limits in P5 and P6
  • Demand occurs in periods P1-P3 for 150, 100, and 300 units, respectively. Demand is allowed to be backordered up to 3 periods for a per unit per period cost of $10:
Screenshot showing demand in P1-P3. The Per Unit Backorder Cost UOM column is omitted and is set to EA for each record. Other omitted columns and their values for all records are: Customer Name = CZ_1, Product Name = Product_1, Status = Include, Demand Status = Include.

With a Per Unit Backorder Cost of 10 and a Maximum Backorder Periods of 3, the optimal solution delivers 150 units in P1, 50 in P2, and 350 in P5:

  • The 200 units of initial inventory are used up as quickly as possible, to keep inventory holding cost to a minimum.
  • To keep total backorder cost as low as possible, the backordered portions of demand from P2 (50 units) and P3 (all 300 units) are produced and delivered as soon as supply is available in P5.

All 550 units are served, 350 of them late, and none are unserved. Total backorder cost is $7,500.

Stepped Backorder Cost

Instead of a number, you can enter a Step Cost Name in the Per Unit Backorder Cost on the Customer Demand table, and define that named schedule in the Step Costs table. This is useful when the cost of lateness is not constant per period, for example when late fees escalate the longer a customer waits.

When Step Costs are used for backorders, Throughput Level is a breakpoint in the number of periods late (1, 2, 3, …), not a quantity breakpoint. For example, consider a step cost named BO_SteppedCost specified on the Step Costs table as follows:

Next, set Per Unit Backorder Cost = BO_SteppedCost on the relevant Customer Demand records. Maximum Backorder Periods can optionally be used in addition to limit how late the demand can be served; the step cost schedule itself does not limit backordering.

The Step Costs table with the schedule as shown above. Step Cost Behavior is set to Stepwise here, see explanation below.
The Per Unit Backorder Cost is now set to the name of the stepped cost that we want to use. Note that you could also set this through a scenario item.

The Step Cost Behavior of the schedule determines how the costs are applied. The three behaviors work as follows:

  • Stepwise: the cost is a per unit cost (not also per period). It is taken from the tier that matches how many periods late the demand is served. For example, for units served 2 periods late, the per unit cost is the cost of the record with Throughput Level = 2.
  • Incremental: the cost is per unit and applies to each late period separately. For the first late period, the cost per late unit is the cost at Throughput Level = 1; for the second late period it is the cost at Throughput Level = 2, and so on. The costs of all late periods are then added up.
  • All Item: the cost is taken from the tier that matches how many periods late the units are, and is then applied on a per unit per period basis. For example, for units 3 periods late, the cost at Throughput Level = 3 is used and total backorder cost = number of units × 3 periods × that cost.

For the BO_SteppedCost schedule above (cost 10, 20, 30 for throughput level 1, 2, 3), the cost for one unit delivered 1, 2, or 3 periods late is:

Please note:

  • Costs are not interpolated between breakpoints.
  • Below the first breakpoint the backorder charge is zero.
  • Beyond the last breakpoint the final tier continues to apply (with Incremental behavior, the last rate continues to apply for each additional late period).
✓

Pro tip

Choose the Step Cost Behavior that matches the commercial rule:

  • Stepwise when a 2-period delay should cost 20 per unit in total.
  • All Item when a 2-period delay should cost 20 per unit for each of the 2 periods.
  • Incremental when the first late period costs 10 and the second adds another 20.

‍

Example: Stepped Cost

Scenarios using these stepped costs with the 3 different step cost behaviors result in the same late quantities and delivery periods as the numeric example above: 50 units delivered three periods late and 300 units delivered two periods late. Backorder costs are then calculated as follows:

In all 3 scenarios 550 units are served, of which 350 late. Different cost structures can lead to different delivery timing and backorder costing decisions in other models and scenarios; in this example the plan happens to stay the same.

✓

Pro tip

  • Make sure the Step Cost Name entered in Per Unit Backorder Cost exactly matches a Step Cost Name in the Step Costs table. A misspelled name may result in late deliveries being modeled without a charge.
  • Start the first tier at Throughput Level = 1 if every late period should be charged.
  • Leave the Throughput Level UOM blank for this period-count use; do not enter a time UOM such as days or weeks to change how lateness is counted.
  • Consider using a dedicated Step Cost Name for backorders, and use the same Step Cost Behavior on all records of that name.

‍

Viewing Results

Backorders add new fields to two existing output tables and introduce a new output table.

New Fields on Existing Output Tables

i

Good to know

On the Optimization Customer, Demand, and Cost To Serve Summary output tables, costs and revenues are recorded in the period the demand occurred (its due period). If (part of) the demand is served late, this is not visible in the period columns of these tables; the details are in the Optimization Demand Backorder Summary.

For example, in the numeric example above, P3 shows 300 units served and 300 (=all) units backordered in the Optimization Demand Summary; these units physically arrive in P5. Use the Optimization Flow Summary to see the physical flows by delivery period.

‍

The Optimization Demand Summary outputs for the numeric example above. The Backordered Quantity and Backorder Cost columns show that 50 units in P2 and 300 units in P3 were backordered for a total cost of $1,500 and $6,000, respectively.
The Optimization Flow Summary outputs for the numeric example above. We see that less than the demanded units are delivered in P2 (50 of 100 demanded), no units are delivered in P3, and the 350 backordered units (50 from P2, 300 from P3) are delivered in P5.

Optimization Demand Backorder Summary

This new output table connects the original demand period with the period in which the late delivery happens. Each record describes one late delivery, defined by its scenario, customer, product, service mode, original due period, and delivery period. A demand split across several delivery periods therefore appears as several records. On-time deliveries do not appear in this table.

The Optimization Demand Backorder Summary outputs for the numeric example above. We see the 2 entries for the backordered demand from P2 (50 units) and from P3 (300 units), which were both delivered in P5. The periods late, backordered quantity, per unit backorder cost, and total backorder cost can be found on this table. Note that the Customer Name (CZ_1), Product Name (Product_1), and Service Mode (all) fields are omitted in this screenshot.
!

Heads up

The Per Unit Backorder Cost output is the total charge per unit for the whole delay, not the rate that was entered. With a numeric input of 10 and delivery three periods late, the output is 30. With the 10/20/30 All Item stepped cost schedule, a three-period delay gives an output of 90. Do not multiply this output by Periods Late again.

‍

Reconciling the Results

For one scenario and a consistent customer, product, and service mode scope:

  1. Group the Optimization Demand Backorder Summary by Demand Period Name. Its Backordered Quantity and Backorder Cost reconcile to the corresponding fields in the Optimization Demand Summary.
  2. Sum Backorder Cost in the Optimization Demand Backorder Summary across the scenario. It reconciles to Total Backorder Cost in the Optimization Network Summary.
  3. Use Delivery Period Name (on Optimization Demand Backorder Summary) together with the Optimization Flow Summary to examine the actual deliveries and capacity use in the catch-up periods.
  4. Review Original Demand Quantity, Served Demand Quantity, Unserved Demand Quantity, and Backordered Quantity on the Optimization Demand Summary. Backordered Quantity is a subset of served quantity; it is not unserved demand.

Each late quantity appears once for its combination of demand and delivery periods, regardless of how many periods late it is. For example, 50 units delivered three periods late counts as 50 backordered, not 150. The table records late fulfillment rather than an ending backlog balance for each period. Demand that is ultimately left unserved does not appear in this table and needs to be tracked separately.

i

Good to know

Eventually served is not the same as served on time. Backordered demand counts as served. To measure on-time service, look at the backordered quantity separately from the served quantity.

‍

Combining Backorders with Maturation Time and Shelf Life

Backorders change when demand may be fulfilled. They do not waive the product’s maturation, expiry, inventory, production, or transportation rules. Three timing checks all need to hold for a late delivery to happen:

  • Customer deadline: the delivery is no later than Maximum Backorder Periods after the demand period (if a maximum is set).
  • Product usability: the product is mature and not expired when it is delivered (if Shelf Life and/or Maturation Time are specified).
  • Calendar boundary: the delivery occurs in a period that exists in the model.

Product Age is a Different Clock from Periods Late

The production period counts as product age 1. Product made in P5 is age 2 in P6 and age 3 in P7. Maturation Time and Shelf Life are time quantities that are converted to period counts (for details see this Help Center article); they are not automatically the same as Maximum Backorder Periods. A product made in P5 and delivered in P6 is age 2, while P3 demand delivered in P6 is 3 periods late. These values describe different things.

Maturation Time

Maximum Backorder Periods limits delivery independently of maturation. Demand can only be served late up to its maximum, so supply that needs to mature and only becomes usable after that point cannot be used for it. Extending the model calendar alone does not change this. Either the allowed delay needs to increase, if customers can genuinely accept it, or an earlier usable source of supply is needed.

Shelf Life

Backorders do not extend shelf life or restart the age of inventory. A late delivery still needs usable product at the time it is delivered, and waiting may cause existing stock to expire. Later production may be needed instead.

Similar interactions can occur with other bottlenecks. For example, if product is made early but there is a transportation bottleneck, late demand can only be served from product that is still within its shelf life when it finally ships. If demand may be served 5 periods late but shelf life is 2 periods, the product needs to be produced in the period it is delivered or the period before (age = 1 in period of production).

Practical Modeling Tips

  • Provide a place to age or hold stock. A valid Inventory Policy with Stocking Site = True and a feasible network path are needed where product waits.
  • Check opening inventory age. A blank Initial Inventory Age means age 1, so opening stock is not assumed to be mature. Use Initial Inventory Age (and UOM) to represent genuinely older stock.
  • Inspect both clocks. Use the Optimization Flow Age Summary and Optimization Inventory Age Summary for product age, and the Optimization Demand Backorder Summary for periods late.

Handling the End of the Model Horizon

The last period in which demand can be served late is the earlier of: original due period + Maximum Backorder Periods, and the final modeled period. A blank maximum means no limit within the horizon, but never beyond it. Consider a model with periods P1–P6:

!

Heads up

Neo does not create delivery periods beyond the model horizon when allowing backorders. For example, when P6 demand is allowed to be a maximum of 3 periods late, periods P7-P9 are not automatically generated. Required (Demand Status = Include) demand that cannot be fulfilled within the horizon and its allowed delay will make the model infeasible.

‍

Demand due in the last periods of the model is the most affected. Some of it may only be servable after the final period, for example because the network is capacity constrained at the end of the horizon, or because lead times or maturation push usable supply beyond the last modeled period. Neo cannot deliver this demand late, because there are no periods left to deliver it in. If this demand has Demand Status = Include, the model becomes infeasible. There are two main ways to handle this:

  1. Set Demand Status = Consider for the affected demand. Apply this to the demand in the last periods, or to all demand. Neo can then leave the demand it cannot serve within the horizon unserved. Consider demand is evaluated against revenue, so make sure a Unit Price is set for the products. Where appropriate, add a Penalty Cost too. This is reported as Unserved Demand Quantity, where it normally represents lost demand but can in this case be the backlog that still needs to be delivered after the model end date.
  2. Extend the model horizon with a recovery tail. Add periods after the last period with demand, so that late deliveries, maturation, and lead times can play out. These added periods do not need any demand of their own. Their purpose is to let backorders be delivered and avoid infeasibility. Do not forget to also update the Model End Date in Model Settings. Make sure supply, production capacity, facility availability, inventory, and transportation are available in the added periods, with realistic costs. Because the added periods only serve to catch up on late demand, you may want to exclude (some of) their costs and statistics when reporting results. Ada can help with this type of post-processing.

If the issue is that demand cannot be served in time because the supply is simply not there, two further options apply:

  1. Provide real earlier usable supply, such as earlier production or correctly aged opening inventory.
  2. Increase Maximum Backorder Periods if customers can genuinely accept the longer delay.

As a more general rule, avoid ending a model in a peak season. The end of the horizon is where demand has the least room to be served late, so a peak there forces Neo to serve it on time or not at all. Where possible, end the model in a period with slack capacity, where late service is unlikely to be needed.

Tips and Best Practices

Backorders are Automatically Enabled

No additional model option is required. Backorders are allowed on every Customer Demand record that has a Per Unit Backorder Cost or a Maximum Backorder Periods > 0.

Compare to a Baseline without Backorders

Leave the backorder fields blank in the Baseline scenario, and use scenario items to populate Per Unit Backorder Cost and Maximum Backorder Periods in the scenarios that allow backorders. Running scenarios with different maximum delays (0, 1, 2, …) quantifies the value of customer flexibility.

Set Backorder Costs with Care when Demand is Optional

When Demand Status = Consider, the cost to serve (including the backorder cost) is compared against revenue. If backorder costs plus other costs exceed revenue, Neo will choose not to serve the demand. Ensure products have realistic prices and compare the Unserved Demand Quantity between scenarios.

Do Not Assume First-Come, First-Served

Enabling backorders does not give older (earlier due) demand priority. Neo decides which demand is served late based on the overall cost. If service priorities matter, they need to be modeled explicitly, for example by using stepped backorder costs which increase by period.

Filter the Backorder Summary

Filter the Optimization Demand Backorder Summary by scenario, and sort by Backorder Cost or Periods Late to quickly see which customers and products are affected most.

Checklist Before Solving

  • There are later periods in which late demand can be delivered.
  • Per Unit Backorder Cost is the intended number or an existing Step Cost Name, and Maximum Backorder Periods is the intended limit (blank = no limit, 0 = no backorders allowed).
  • The cost is expressed on the same basis as the model’s quantities and currency, and periods are the intended lateness buckets.
  • Demand Status reflects whether fulfillment is mandatory or optional.
  • Real supply, capacity, inventory, and lanes are available in the catch-up periods, and maturation, shelf life, and opening inventory age allow usable product at delivery.
  • The last periods of the model leave enough time for the intended recovery.

Checklist After Solving

  • Confirm the solve status. If Infeasible, consider running an Infeasibility Diagnosis next.
  • Compare served, unserved, and backordered quantities with demand.
  • Check original Demand Period, Delivery Period, and Periods Late in the Optimization Demand Backorder Summary, and reconcile its Backorder Cost to the Optimization Demand Summary and the Optimization Network Summary.

Troubleshooting

Other Helpful Resources

The following Help Center articles cover several modeling concepts touched upon in this article in more detail:

Please reach out to our Support team on support@optilogic.com for any questions or feedback.

Backorders enable Cosmic Frog’s network optimization engine (Neo) to fulfill customer demand in a later period than the period in which it was due, at a cost that you specify. Instead of forcing every unit to be delivered exactly on time, Neo can weigh the cost of serving late against the cost of the alternatives: building capacity for every peak, prebuilding and holding inventory, or leaving demand unserved. It helps answer questions such as:

  • Is it cheaper to deliver part of a demand peak late than to size the network to serve all of it on time?
  • After a production outage or supply disruption, how much demand is served late, how late, and at what cost?
  • Should we hold prebuilt inventory close to customers, or accept some late deliveries?
  • What is customer tolerance for delay worth to us? What if customers accepted one more period of lateness?

A backorder is demand that is fulfilled in a modeled period later than its original due period.

Backordering is a permission, not a requirement. Neo can still serve demand on time, and it will choose late service only where this lowers the overall cost of the network or where it is the only way to serve the demand.

Backorders are set up with two new fields on the Customer Demand table and are reported in new fields on existing output tables as well as in a new output table, the Optimization Demand Backorder Summary. Backorders can also be combined with stepped costs to make the cost of late delivery depend non-linearly on how late the demand is served.

Quick Start

If you want to get going with backorders quickly, follow these steps:

  1. Use a multi-period model: backorders need later periods in which late demand can be delivered.
  2. Set the cost of late delivery: on the relevant Customer Demand records, specify a Per Unit Backorder Cost.
  3. Optionally limit the delay: enter a whole number greater than 0 in Maximum Backorder Periods to cap how many periods late demand may be served.
  4. Run Neo: no additional model option needs to be enabled; backorders are automatically allowed on the demand records where they are specified.
  5. Review the results: check Total Backorder Cost on the Optimization Network Summary, and the demand period, delivery period, and periods late in the Optimization Demand Backorder Summary.

Alternatively, you can also get started using Ada, Optilogic’s agentic AI, and ask her questions along the way. For example, start with a prompt like “Create a small Neo model which uses the backorder fields on the customer demand table in a scenario. Make sure that in this scenario part of the demand is served late”.

Why Backorders Matter

Many supply chains do not serve every order exactly when it is due. Customers often accept a delay, whether this is explicit (a contractual lead time or delivery window) or implicit (an order that gets shipped once stock arrives). Models that insist on 100% on-time service can overstate the capacity and inventory a network needs and can even be infeasible when a real network would simply deliver somewhat late.

Without backorders, the usual workaround is to leave demand optional (Demand Status = Consider) so that the model can drop what it cannot serve. This hides the difference between demand that is delivered late and demand that is lost altogether.

Backorders let Neo treat late delivery as an optimization decision with its own cost. Late service is then evaluated together with production, sourcing, inventory, and transportation decisions, rather than as a manual after-the-fact adjustment. The outputs quantify how much demand is served late, how late it is, and what this costs.

✓

Pro tip

Backorders and unserved demand are different economic choices. Per Unit Backorder Cost prices demand that is delivered late; Penalty Cost (also on Customer Demand) prices demand that is never served.

‍

When to Use Backorders

Use backorders when customers can accept a delay and you want Neo to decide whether, how much, and how late demand should be served. The following are common situations where backorders may be appropriate:

Rule of thumb question: Is serving demand late a real option that I want Neo to evaluate, with a cost I can put a number on?

  • Yes: Backorders are likely the right tool.
  • No: If demand must always be served in its due period, leave the backorder fields blank. If demand may simply be lost if it cannot be served when due, use Demand Status = Consider, optionally with a Penalty Cost.

How Backorders Work

Customer Demand: Two New Fields

Backorders are configured on each applicable record of the Customer Demand table. Two new fields are available:

Combining the two fields gives the following behavior:

!

Heads up

Late service at no charge is rarely realistic. If you set only Maximum Backorder Periods, Neo can treat late delivery as free, and may deliver late even when on-time service would cost slightly more. It is recommended to specify a Per Unit Backorder Cost whenever backorders are allowed.

‍

Lateness is Counted in Model Periods

The backorder fields do not introduce a separate time unit. Lateness is counted in model periods, not days. With weekly periods, one period late means one week late; with monthly periods it means one month late. Periods of unequal length still count as one period each. Use a period structure that matches the lateness granularity that is meaningful for your business.

A multi-period model is required, because late deliveries need later periods in which to be served. The last period in which demand can be served late is the earlier of: the original demand period plus Maximum Backorder Periods, and the final period of the model (see Handling the End of the Model Horizon).

Demand Status: Include versus Consider

Demand does not need to be set to Consider to allow backorders. As soon as a Per Unit Backorder Cost or Maximum Backorder Periods > 0 is set, backorders are automatically allowed. How Demand Status interacts with this is as follows:

  • Demand Status = Include: all of the demand must still be served, either on time or within its allowed backorder window. Backorders give Neo more flexibility in when to serve, but not whether to serve. If not all demand can be served within the allowed window, the model will be infeasible.
  • Demand Status = Consider: Neo may leave demand unserved if this is more economical, according to revenues, costs, and any Penalty Cost. Backorders add late delivery as another option; they do not require Neo to use it. Think carefully about the backorder cost here: if the backorder cost plus the other costs to serve exceed the revenue (based on a product’s Unit Price), Neo can choose to not serve the demand at all.

Configuring Backorder Costs

Numeric Backorder Cost

When Per Unit Backorder Cost is a number, the backorder cost is calculated as:

Backorder cost = late quantity (/volume/weight) × Per Unit Backorder Cost × periods late

On-time deliveries incur no backorder charge. If one demand record is split over several delivery periods, the cost is calculated separately for each late portion, and the results are added up. Backorder cost is an additional modeled cost; it does not replace production, inventory, transportation, or other costs.

Example: Numeric Cost

Consider the following details of a simple example model:

  • One manufacturing location MFG_1, 1 customer location CZ_1, 1 product Product_1
  • Six weekly periods, P1-P6
  • Initial inventory of 200 units of Product_1 at MFG_1
  • To encourage serving demand as soon as possible, inventory holding costs are modeled:
    • Unit Value of $50 (Products table)
    • Inventory Carrying Cost Percentage of 20% (Model Settings table)
  • Due to a disruption, MFG_1 cannot produce anything during P1-P4; no limits in P5 and P6
  • Demand occurs in periods P1-P3 for 150, 100, and 300 units, respectively. Demand is allowed to be backordered up to 3 periods for a per unit per period cost of $10:
Screenshot showing demand in P1-P3. The Per Unit Backorder Cost UOM column is omitted and is set to EA for each record. Other omitted columns and their values for all records are: Customer Name = CZ_1, Product Name = Product_1, Status = Include, Demand Status = Include.

With a Per Unit Backorder Cost of 10 and a Maximum Backorder Periods of 3, the optimal solution delivers 150 units in P1, 50 in P2, and 350 in P5:

  • The 200 units of initial inventory are used up as quickly as possible, to keep inventory holding cost to a minimum.
  • To keep total backorder cost as low as possible, the backordered portions of demand from P2 (50 units) and P3 (all 300 units) are produced and delivered as soon as supply is available in P5.

All 550 units are served, 350 of them late, and none are unserved. Total backorder cost is $7,500.

Stepped Backorder Cost

Instead of a number, you can enter a Step Cost Name in the Per Unit Backorder Cost on the Customer Demand table, and define that named schedule in the Step Costs table. This is useful when the cost of lateness is not constant per period, for example when late fees escalate the longer a customer waits.

When Step Costs are used for backorders, Throughput Level is a breakpoint in the number of periods late (1, 2, 3, …), not a quantity breakpoint. For example, consider a step cost named BO_SteppedCost specified on the Step Costs table as follows:

Next, set Per Unit Backorder Cost = BO_SteppedCost on the relevant Customer Demand records. Maximum Backorder Periods can optionally be used in addition to limit how late the demand can be served; the step cost schedule itself does not limit backordering.

The Step Costs table with the schedule as shown above. Step Cost Behavior is set to Stepwise here, see explanation below.
The Per Unit Backorder Cost is now set to the name of the stepped cost that we want to use. Note that you could also set this through a scenario item.

The Step Cost Behavior of the schedule determines how the costs are applied. The three behaviors work as follows:

  • Stepwise: the cost is a per unit cost (not also per period). It is taken from the tier that matches how many periods late the demand is served. For example, for units served 2 periods late, the per unit cost is the cost of the record with Throughput Level = 2.
  • Incremental: the cost is per unit and applies to each late period separately. For the first late period, the cost per late unit is the cost at Throughput Level = 1; for the second late period it is the cost at Throughput Level = 2, and so on. The costs of all late periods are then added up.
  • All Item: the cost is taken from the tier that matches how many periods late the units are, and is then applied on a per unit per period basis. For example, for units 3 periods late, the cost at Throughput Level = 3 is used and total backorder cost = number of units × 3 periods × that cost.

For the BO_SteppedCost schedule above (cost 10, 20, 30 for throughput level 1, 2, 3), the cost for one unit delivered 1, 2, or 3 periods late is:

Please note:

  • Costs are not interpolated between breakpoints.
  • Below the first breakpoint the backorder charge is zero.
  • Beyond the last breakpoint the final tier continues to apply (with Incremental behavior, the last rate continues to apply for each additional late period).
✓

Pro tip

Choose the Step Cost Behavior that matches the commercial rule:

  • Stepwise when a 2-period delay should cost 20 per unit in total.
  • All Item when a 2-period delay should cost 20 per unit for each of the 2 periods.
  • Incremental when the first late period costs 10 and the second adds another 20.

‍

Example: Stepped Cost

Scenarios using these stepped costs with the 3 different step cost behaviors result in the same late quantities and delivery periods as the numeric example above: 50 units delivered three periods late and 300 units delivered two periods late. Backorder costs are then calculated as follows:

In all 3 scenarios 550 units are served, of which 350 late. Different cost structures can lead to different delivery timing and backorder costing decisions in other models and scenarios; in this example the plan happens to stay the same.

✓

Pro tip

  • Make sure the Step Cost Name entered in Per Unit Backorder Cost exactly matches a Step Cost Name in the Step Costs table. A misspelled name may result in late deliveries being modeled without a charge.
  • Start the first tier at Throughput Level = 1 if every late period should be charged.
  • Leave the Throughput Level UOM blank for this period-count use; do not enter a time UOM such as days or weeks to change how lateness is counted.
  • Consider using a dedicated Step Cost Name for backorders, and use the same Step Cost Behavior on all records of that name.

‍

Viewing Results

Backorders add new fields to two existing output tables and introduce a new output table.

New Fields on Existing Output Tables

i

Good to know

On the Optimization Customer, Demand, and Cost To Serve Summary output tables, costs and revenues are recorded in the period the demand occurred (its due period). If (part of) the demand is served late, this is not visible in the period columns of these tables; the details are in the Optimization Demand Backorder Summary.

For example, in the numeric example above, P3 shows 300 units served and 300 (=all) units backordered in the Optimization Demand Summary; these units physically arrive in P5. Use the Optimization Flow Summary to see the physical flows by delivery period.

‍

The Optimization Demand Summary outputs for the numeric example above. The Backordered Quantity and Backorder Cost columns show that 50 units in P2 and 300 units in P3 were backordered for a total cost of $1,500 and $6,000, respectively.
The Optimization Flow Summary outputs for the numeric example above. We see that less than the demanded units are delivered in P2 (50 of 100 demanded), no units are delivered in P3, and the 350 backordered units (50 from P2, 300 from P3) are delivered in P5.

Optimization Demand Backorder Summary

This new output table connects the original demand period with the period in which the late delivery happens. Each record describes one late delivery, defined by its scenario, customer, product, service mode, original due period, and delivery period. A demand split across several delivery periods therefore appears as several records. On-time deliveries do not appear in this table.

The Optimization Demand Backorder Summary outputs for the numeric example above. We see the 2 entries for the backordered demand from P2 (50 units) and from P3 (300 units), which were both delivered in P5. The periods late, backordered quantity, per unit backorder cost, and total backorder cost can be found on this table. Note that the Customer Name (CZ_1), Product Name (Product_1), and Service Mode (all) fields are omitted in this screenshot.
!

Heads up

The Per Unit Backorder Cost output is the total charge per unit for the whole delay, not the rate that was entered. With a numeric input of 10 and delivery three periods late, the output is 30. With the 10/20/30 All Item stepped cost schedule, a three-period delay gives an output of 90. Do not multiply this output by Periods Late again.

‍

Reconciling the Results

For one scenario and a consistent customer, product, and service mode scope:

  1. Group the Optimization Demand Backorder Summary by Demand Period Name. Its Backordered Quantity and Backorder Cost reconcile to the corresponding fields in the Optimization Demand Summary.
  2. Sum Backorder Cost in the Optimization Demand Backorder Summary across the scenario. It reconciles to Total Backorder Cost in the Optimization Network Summary.
  3. Use Delivery Period Name (on Optimization Demand Backorder Summary) together with the Optimization Flow Summary to examine the actual deliveries and capacity use in the catch-up periods.
  4. Review Original Demand Quantity, Served Demand Quantity, Unserved Demand Quantity, and Backordered Quantity on the Optimization Demand Summary. Backordered Quantity is a subset of served quantity; it is not unserved demand.

Each late quantity appears once for its combination of demand and delivery periods, regardless of how many periods late it is. For example, 50 units delivered three periods late counts as 50 backordered, not 150. The table records late fulfillment rather than an ending backlog balance for each period. Demand that is ultimately left unserved does not appear in this table and needs to be tracked separately.

i

Good to know

Eventually served is not the same as served on time. Backordered demand counts as served. To measure on-time service, look at the backordered quantity separately from the served quantity.

‍

Combining Backorders with Maturation Time and Shelf Life

Backorders change when demand may be fulfilled. They do not waive the product’s maturation, expiry, inventory, production, or transportation rules. Three timing checks all need to hold for a late delivery to happen:

  • Customer deadline: the delivery is no later than Maximum Backorder Periods after the demand period (if a maximum is set).
  • Product usability: the product is mature and not expired when it is delivered (if Shelf Life and/or Maturation Time are specified).
  • Calendar boundary: the delivery occurs in a period that exists in the model.

Product Age is a Different Clock from Periods Late

The production period counts as product age 1. Product made in P5 is age 2 in P6 and age 3 in P7. Maturation Time and Shelf Life are time quantities that are converted to period counts (for details see this Help Center article); they are not automatically the same as Maximum Backorder Periods. A product made in P5 and delivered in P6 is age 2, while P3 demand delivered in P6 is 3 periods late. These values describe different things.

Maturation Time

Maximum Backorder Periods limits delivery independently of maturation. Demand can only be served late up to its maximum, so supply that needs to mature and only becomes usable after that point cannot be used for it. Extending the model calendar alone does not change this. Either the allowed delay needs to increase, if customers can genuinely accept it, or an earlier usable source of supply is needed.

Shelf Life

Backorders do not extend shelf life or restart the age of inventory. A late delivery still needs usable product at the time it is delivered, and waiting may cause existing stock to expire. Later production may be needed instead.

Similar interactions can occur with other bottlenecks. For example, if product is made early but there is a transportation bottleneck, late demand can only be served from product that is still within its shelf life when it finally ships. If demand may be served 5 periods late but shelf life is 2 periods, the product needs to be produced in the period it is delivered or the period before (age = 1 in period of production).

Practical Modeling Tips

  • Provide a place to age or hold stock. A valid Inventory Policy with Stocking Site = True and a feasible network path are needed where product waits.
  • Check opening inventory age. A blank Initial Inventory Age means age 1, so opening stock is not assumed to be mature. Use Initial Inventory Age (and UOM) to represent genuinely older stock.
  • Inspect both clocks. Use the Optimization Flow Age Summary and Optimization Inventory Age Summary for product age, and the Optimization Demand Backorder Summary for periods late.

Handling the End of the Model Horizon

The last period in which demand can be served late is the earlier of: original due period + Maximum Backorder Periods, and the final modeled period. A blank maximum means no limit within the horizon, but never beyond it. Consider a model with periods P1–P6:

!

Heads up

Neo does not create delivery periods beyond the model horizon when allowing backorders. For example, when P6 demand is allowed to be a maximum of 3 periods late, periods P7-P9 are not automatically generated. Required (Demand Status = Include) demand that cannot be fulfilled within the horizon and its allowed delay will make the model infeasible.

‍

Demand due in the last periods of the model is the most affected. Some of it may only be servable after the final period, for example because the network is capacity constrained at the end of the horizon, or because lead times or maturation push usable supply beyond the last modeled period. Neo cannot deliver this demand late, because there are no periods left to deliver it in. If this demand has Demand Status = Include, the model becomes infeasible. There are two main ways to handle this:

  1. Set Demand Status = Consider for the affected demand. Apply this to the demand in the last periods, or to all demand. Neo can then leave the demand it cannot serve within the horizon unserved. Consider demand is evaluated against revenue, so make sure a Unit Price is set for the products. Where appropriate, add a Penalty Cost too. This is reported as Unserved Demand Quantity, where it normally represents lost demand but can in this case be the backlog that still needs to be delivered after the model end date.
  2. Extend the model horizon with a recovery tail. Add periods after the last period with demand, so that late deliveries, maturation, and lead times can play out. These added periods do not need any demand of their own. Their purpose is to let backorders be delivered and avoid infeasibility. Do not forget to also update the Model End Date in Model Settings. Make sure supply, production capacity, facility availability, inventory, and transportation are available in the added periods, with realistic costs. Because the added periods only serve to catch up on late demand, you may want to exclude (some of) their costs and statistics when reporting results. Ada can help with this type of post-processing.

If the issue is that demand cannot be served in time because the supply is simply not there, two further options apply:

  1. Provide real earlier usable supply, such as earlier production or correctly aged opening inventory.
  2. Increase Maximum Backorder Periods if customers can genuinely accept the longer delay.

As a more general rule, avoid ending a model in a peak season. The end of the horizon is where demand has the least room to be served late, so a peak there forces Neo to serve it on time or not at all. Where possible, end the model in a period with slack capacity, where late service is unlikely to be needed.

Tips and Best Practices

Backorders are Automatically Enabled

No additional model option is required. Backorders are allowed on every Customer Demand record that has a Per Unit Backorder Cost or a Maximum Backorder Periods > 0.

Compare to a Baseline without Backorders

Leave the backorder fields blank in the Baseline scenario, and use scenario items to populate Per Unit Backorder Cost and Maximum Backorder Periods in the scenarios that allow backorders. Running scenarios with different maximum delays (0, 1, 2, …) quantifies the value of customer flexibility.

Set Backorder Costs with Care when Demand is Optional

When Demand Status = Consider, the cost to serve (including the backorder cost) is compared against revenue. If backorder costs plus other costs exceed revenue, Neo will choose not to serve the demand. Ensure products have realistic prices and compare the Unserved Demand Quantity between scenarios.

Do Not Assume First-Come, First-Served

Enabling backorders does not give older (earlier due) demand priority. Neo decides which demand is served late based on the overall cost. If service priorities matter, they need to be modeled explicitly, for example by using stepped backorder costs which increase by period.

Filter the Backorder Summary

Filter the Optimization Demand Backorder Summary by scenario, and sort by Backorder Cost or Periods Late to quickly see which customers and products are affected most.

Checklist Before Solving

  • There are later periods in which late demand can be delivered.
  • Per Unit Backorder Cost is the intended number or an existing Step Cost Name, and Maximum Backorder Periods is the intended limit (blank = no limit, 0 = no backorders allowed).
  • The cost is expressed on the same basis as the model’s quantities and currency, and periods are the intended lateness buckets.
  • Demand Status reflects whether fulfillment is mandatory or optional.
  • Real supply, capacity, inventory, and lanes are available in the catch-up periods, and maturation, shelf life, and opening inventory age allow usable product at delivery.
  • The last periods of the model leave enough time for the intended recovery.

Checklist After Solving

  • Confirm the solve status. If Infeasible, consider running an Infeasibility Diagnosis next.
  • Compare served, unserved, and backordered quantities with demand.
  • Check original Demand Period, Delivery Period, and Periods Late in the Optimization Demand Backorder Summary, and reconcile its Backorder Cost to the Optimization Demand Summary and the Optimization Network Summary.

Troubleshooting

Other Helpful Resources

The following Help Center articles cover several modeling concepts touched upon in this article in more detail:

Please reach out to our Support team on support@optilogic.com for any questions or feedback.

Have More Questions?

Contact Support

Get in touch

Contact Sales

Get in touch

Visit Frogger Pond Community

Visit our Community